Celec Regains Path To Terminate Failed Esmeraldas III Contract
Energy

Celec Regains Path To Terminate Failed Esmeraldas III Contract

Chip MorenoChip Moreno||Source: Primicias

Contract status

Celec says it has recovered the ability to continue the administrative process against ATM for the failed Esmeraldas III thermal project.

The change follows the July 15, 2026 archive of an emergency arbitration process. Those measures had blocked Celec for about a year from terminating the contract, executing guarantees, or applying fines.

As of July 28, 2026, the termination had not yet been registered in Sercop.

Project details

Celec contracted ATM on August 9, 2024 to build the 91 MW Esmeraldas III thermoelectric plant for USD 89.9 million.

The plant was supposed to enter operation in late 2024 or early 2025 as part of Ecuador's emergency thermal-generation response to the 2024 power crisis, when rationing reached up to 14 hours.

According to the source, 30 of 48 turbogenerators were configured for 50 Hz, while Ecuador's grid uses 60 Hz.

Fines connected to the project are close to USD 23 million. The contract includes a clause allowing unilateral termination when fines exceed 5% of the contract value.

Business signal

This is an energy-security and procurement-risk story.

Ecuador needed fast thermal generation to reduce exposure to hydrological stress. Instead, the Esmeraldas III dispute highlights the execution risk of emergency procurement, technical compatibility, imported equipment, contractual guarantees, and arbitration-driven delays.

What to watch

  • Whether Celec registers unilateral termination in Sercop
  • Whether guarantees and fines are executed
  • Whether replacement capacity is contracted before the next dry-season stress window
  • Whether future emergency procurement receives tighter technical controls

Source: Primicias.

Source

Primicias — “Celec tiene via libre para terminar contrato electrico fallido con ATM, pero aun no registra la decision en Sercop”

View original

Report an article problem

Tell us what seems incorrect or outdated. Email is optional.

CelecATMEsmeraldas IIIthermal power
Companies: Celec, ATM
Regions: Esmeraldas, Ecuador
Share

For business readers

Need a focused answer to an Ecuador business question?

Request a separately scoped 30-minute research consult with a written summary. A request does not update or verify this archived article. This is business research context, not legal, tax, or investment advice.

Request a research consult
Research Support

Support the EcuadorBrief archive.

Research support helps fund source monitoring, corrections, and hosting.

Newsletter signups are unavailable

Browse the article archive or join Chip's personal newsletter for updates.

Join Chip's personal newsletter

Related Coverage

Energy

Ecuador Completes Nationwide Electrical Maintenance to Bolster Transmission System and Energy Security

Ecuador's state-owned electricity companies, Celec EP and CNEL EP, successfully completed scheduled maintenance on transmission and distribution substations across 15 provinces. The operations, conducted early on October 17, 2026, aimed to strengthen the National Transmission System and enhance energy security.

eluniverso.com; vistazo.com|
Energy

Ecuador Resumes Colombian Crude Oil Transport Through National Pipelines, Projecting Annual Revenue of USD 16.8 Million

Petroecuador reported on October 17, 2026, the resumption of Colombian crude oil transport via Ecuadorian pipelines, authorized by the Government of Daniel Noboa. This service for Ecopetrol and Amerisur is projected to generate USD 16.8 million annually for the Ecuadorian State, with an average daily transport of 11,900 barrels.

vistazo.com|
Energy

Ecuador Implements Electrical Maintenance and Consumption Reductions Amid El Niño Preparations

Ecuador's Ministry of Environment and Energy announced contingency maintenance for electrical transmission and distribution systems across fifteen provinces on October 17, 2026, from 03:00 to 06:00. This initiative, part of the government's El Niño preparedness, involves 54 operations.

eluniverso.com; eluniverso.com; primicias.ec|
Energy

Ecuador–Peru power link: two dated license announcements

Public 2023 and 2026 license announcements for the 500-kV power link, plus the IDB's implementation status.

Primicias; Vistazo|
Energy

Progen Investigation Expands to 30 People as Ecuador Reopens Power-Contract Questions

Ecuador’s Fiscalía is seeking to add nine people to the Progen case, bringing the total number of investigated individuals to 30. The investigation concerns contracts for thermal generators and a reported potential loss above USD 100 million.

Primicias|
Opens WhatsApp with a pre-filled message