Energy

Ecuador's 920 MW Thermal Plan: $696 Million Committed, 490 MW in Unfulfilled Prior Commitments

Chip MorenoChip Moreno||Source: Expreso

Ecuador's government announced on April 20 plans to incorporate 920 MW of thermal generation capacity in 2026, the latest in a series of evolving energy targets.

The Plan

ComponentCapacityInvestment
Generation rental (fast-install)525 MW$315.54 million
Equipment purchase & replacement395 MW$381.30 million
Total920 MW$696.84 million

Separately, the Plan de Expansión de Generación 2023–2032 (Master Expansion Plan) targets an additional 509 MW from hydroelectric, thermal, and non-conventional renewable energy sources for 2026.

Current Interim Solutions

SourceCapacityStatus
Three barges300 MW (combined)Operational
El Descanso II thermal~17 MWOperational
Vesubio thermal~17 MWOperational
Esmeraldas III (partial)30 MW (of failed 91 MW project)In plan
Total active~334 MW

Unfulfilled Commitments

Two major prior commitments remain unconcretized:

  • 260 MW rental at Pascuales
  • 230 MW barge rental

Total unfulfilled: ~490 MW — more than half the new 920 MW target.

The Credibility Problem

Energy sector analyst Fernando Salinas characterized the situation: "Political discourse dominates rather than planning of a strategic sector."

Engineer Marco Acuña noted that contracted generation facilities could take at least one year to deliver, and larger projects longer.

The government has revised its energy capacity target three times in five months — raising questions about institutional planning capacity within Celec (Corporación Eléctrica del Ecuador) and Cenace (Operador Nacional de Electricidad).

Demand Context

DateDemand
Normal average4,200 MW
March 18, 20265,274 MW
April 10, 20265,333 MW
April 14, 20265,374 MW (record)
Annual growth rate4–5%

Demand growth is driven by data centers and sector electrification. The 28% gap between normal average and peak demand represents the margin that must be covered by dispatchable generation.

What to Watch

  • Contract execution timelines. The 525 MW rental program is the fastest path to capacity. Monitor contract awards and commissioning dates — any slippage compresses the window before the July–November dry season
  • Mazar and Amaluza reservoir levels. Both reservoirs are declining (Mazar at 2,131m, 16m above critical; Amaluza at 1,981m, 6m above minimum). If the dry season accelerates decline, thermal backup becomes critical sooner
  • 490 MW unfulfilled commitments. Pascuales (260 MW) and the barge rental (230 MW) were announced previously. Their continued non-delivery may equally affect the new 920 MW target
  • Esmeraldas III status. Only 30 MW of a failed 91 MW project is included. The original project's shortfall represents unrecovered capacity investment

Source: Expreso

Source

Expreso — "Plan eléctrico de Ecuador avanza a oscuras y sin rumbo claro"

View original
electricitythermalCelecCenaceinvestmentcapacity
Companies: Celec, Cenace
Regions: National
Share
Research Support

Support daily Ecuador business intelligence.

Research support funds source monitoring, data checks, editing, publishing, and sector coverage for professionals tracking Ecuador.

Daily Briefing

Ecuador business intelligence, delivered at 6 AM ECT.

Related Coverage

Energy

Ecuador Updates Permit for $277.7 Million Peru Power Interconnector

Ecuador’s environmental-license update advances the Peru interconnection project. The next test is construction and commissioning against the stated 2029 target.

Primicias; Vistazo|
Energy

ITT Equipment Failure Cut Output to About 15,000 Barrels a Day

An ITT processing-system failure interrupted production beginning September 6. The latest cited operating data precede today, so full restoration remains unverified.

Primicias|
Energy

Paute Inflows Enter the Dry Season Below Historical Benchmarks

Ecuador entered the September 2026-March 2027 dry season with below-historical inflows across the Paute system. Mazar averaged 56 m³/s in August versus a historical 90 m³/s, while Paute basin flow averaged 94.8 m³/s against a historical 136.4 m³/s.

Primicias|
Finance

Mabe Commits $35 Million to New Guayaquil Washing Plant

Mabe, a major appliance manufacturer, is investing $35 million in a new washing machine manufacturing plant in Guayaquil, Ecuador. Scheduled to begin operations in early 2027, this facility is projected to produce over 90,000 units annually for local and regional markets.

eluniverso.com|
Finance

El Niño 2026-2027: Anticipating Economic Impact on Ecuador's Productive Sector

Ecuador's productive sector faces potential significant economic impact from the strengthening El Niño phenomenon, with historical data from 1997-1998 showing 52.8% of national losses absorbed by businesses. Current forecasts indicate a high probability of a historic intensity event by late 2026, emphasizing the need for operational resilience.

primicias.ec; primicias.ec; eluniverso.com|
Opens WhatsApp with a pre-filled message