Publishing is paused. This is a dated archive; older articles and guides may be outdated or unreviewed. Contact Chip about a correction.
Energy

Ecuador's 920 MW Thermal Plan: $696 Million Committed, 490 MW in Unfulfilled Prior Commitments

Chip MorenoChip Moreno||Source: Expreso

Ecuador's government announced on April 20 plans to incorporate 920 MW of thermal generation capacity in 2026, the latest in a series of evolving energy targets.

The Plan

ComponentCapacityInvestment
Generation rental (fast-install)525 MW$315.54 million
Equipment purchase & replacement395 MW$381.30 million
Total920 MW$696.84 million

Separately, the Plan de Expansión de Generación 2023–2032 (Master Expansion Plan) targets an additional 509 MW from hydroelectric, thermal, and non-conventional renewable energy sources for 2026.

Current Interim Solutions

SourceCapacityStatus
Three barges300 MW (combined)Operational
El Descanso II thermal~17 MWOperational
Vesubio thermal~17 MWOperational
Esmeraldas III (partial)30 MW (of failed 91 MW project)In plan
Total active~334 MW—

Unfulfilled Commitments

Two major prior commitments remain unconcretized:

  • 260 MW rental at Pascuales
  • 230 MW barge rental

Total unfulfilled: ~490 MW — more than half the new 920 MW target.

The Credibility Problem

Energy sector analyst Fernando Salinas characterized the situation: "Political discourse dominates rather than planning of a strategic sector."

Engineer Marco Acuña noted that contracted generation facilities could take at least one year to deliver, and larger projects longer.

The government has revised its energy capacity target three times in five months — raising questions about institutional planning capacity within Celec (Corporación Eléctrica del Ecuador) and Cenace (Operador Nacional de Electricidad).

Demand Context

DateDemand
Normal average4,200 MW
March 18, 20265,274 MW
April 10, 20265,333 MW
April 14, 20265,374 MW (record)
Annual growth rate4–5%

Demand growth is driven by data centers and sector electrification. The 28% gap between normal average and peak demand represents the margin that must be covered by dispatchable generation.

What to Watch

  • Contract execution timelines. The 525 MW rental program is the fastest path to capacity. Monitor contract awards and commissioning dates — any slippage compresses the window before the July–November dry season
  • Mazar and Amaluza reservoir levels. Both reservoirs are declining (Mazar at 2,131m, 16m above critical; Amaluza at 1,981m, 6m above minimum). If the dry season accelerates decline, thermal backup becomes critical sooner
  • 490 MW unfulfilled commitments. Pascuales (260 MW) and the barge rental (230 MW) were announced previously. Their continued non-delivery may equally affect the new 920 MW target
  • Esmeraldas III status. Only 30 MW of a failed 91 MW project is included. The original project's shortfall represents unrecovered capacity investment

Source: Expreso

Source

Expreso — “Plan eléctrico de Ecuador avanza a oscuras y sin rumbo claro”

View original
electricitythermalCelecCenaceinvestmentcapacity
Companies: Celec, Cenace
Regions: National
Share
Research Support

Support the EcuadorBrief archive.

Research support helps fund review, corrections, and hosting. New publishing is paused.

Newsletter paused

EcuadorBrief is not sending daily briefings while the archive is under review.

Join Chip's personal newsletter

Related Coverage

Energy

Ecuador Bolsters Thermoelectric Capacity Amid Dry Season and El Niño Concerns

Ecuador's National Electricity Operator Cenace reports an average thermoelectric generation of 875 MW between September 1 and September 23, 2026, contributing approximately 19% of national demand. This increase is partly due to two new generation barges, which began operation on September 21, 2026, adding 200 MW.

primicias.ec; primicias.ec; primicias.ec|
Energy

Ecuador's Oil Production Recovers, Government Seeks Private Investment for Sacha Field

Ecuador's average oil production reached 460,562 barrels per day from January to August 2026, marking an 8.1% recovery from the previous year's pipeline disruptions. The government is actively pursuing private investment for the Sacha oil field, with interest from UAE companies, following a previous unfinalized process in 2025.

primicias.ec; primicias.ec|
Energy

Ecuador's Oil Production Targets Face Lower Projections from Central Bank Amidst Shifting Price Outlook

Ecuador's Ministry of Energy aims for 500,000 barrels per day by December 2026, but the Central Bank of Ecuador projects a lower average of 463,013 bpd for 2027. Oil revenues increased significantly in 2026, while future price forecasts anticipate a market correction despite current high prices.

primicias.ec|
Real Estate & Development

Ambiensa Opens New York Headquarters to Facilitate Property Acquisition for Ecuadorian Migrants

Real estate developer Ambiensa has officially opened its new headquarters in New York, United States. The office aims to provide direct service to Ecuadorian residents seeking to acquire property and consolidate assets in their home nation, offering a new direct credit modality and guidance on national housing programs.

eluniverso.com|
Energy

Ecuador Implements Energy Measures Amid El Niño Threat and Long-Term Sustainability Goals

Ecuador's Ministry of Environment and Energy is coordinating with industries to manage energy supply during the El Niño phenomenon. High-voltage consumers are asked to voluntarily disconnect one day a week, while the government also plans to contract additional electricity generation barcazas.

eluniverso.com; vistazo.com; vistazo.com|
Opens WhatsApp with a pre-filled message