Villonaco III Advances With 112.1 MW Capacity and USD 200M-Plus Private Investment
Energy

Villonaco III Advances With 112.1 MW Capacity and USD 200M-Plus Private Investment

Chip MorenoChip Moreno||Source: El Universo

Villonaco III has reached a visible equipment-delivery milestone: 30 of 57 wind-turbine blades have arrived in Ecuador through Puerto Bolívar and are scheduled for transport to Loja.

Project configuration

The project is planned for Cerro Huayrapamba, between Loja and Catamayo, with 19 wind turbines. Each turbine is designed to produce 5.9 MW at an installation altitude of approximately 3,000 meters above sea level.

The planned total capacity is 112.1 MW, which would make Villonaco III the largest wind project built in Ecuador. The movement of the blades to the project is expected to begin in mid-September, subject to the stated conditions.

The delivery milestone changes the project’s evidence base. It is no longer only a concession and financing proposition; large physical components are now entering the logistics chain. It remains, however, a construction-stage asset.

Capital structure and timing

Villonaco III represents more than USD 200 million in private investment under a 25-year concession described as requiring no public resources. The concession took effect on January 15, 2025, and construction began on July 7, 2025.

Reported physical progress reached 54.53% by June 2026. Commercial operation is targeted for the third quarter of 2027. The schedule is therefore still exposed to transport, civil works, turbine installation, grid connection, testing, and commissioning risk.

Financing is backed by BID Invest, Proparco, and FMO. That lender group is a positive signal for project bankability, but it is not a substitute for delivered output or a completed operating asset.

Local economic commitments

The project plans for 60% local labor and 50% local suppliers. After commercial operation begins, 12% of profits is expected to be reinvested in the direct areas of influence.

These commitments should be treated as monitoring variables. Their value for Loja and Catamayo will depend on definitions, reporting, procurement access, and whether the commitments persist beyond the construction peak.

Brief assessment

Villonaco III is an execution story with three separate milestones: component arrival, construction completion, and commercial operation. The first is now observable. The second remains in progress, and the third remains a target.

The investment case should therefore track more than megawatts. The next useful disclosures are blade transport, turbine installation, grid-connection status, updated physical progress, and confirmation of the commercial-operation schedule. The final tariff, contracted buyer, annual output, and delivered operating date are not established by the current milestone.

The signal is constructive but bounded: Ecuador is converting private capital into a large renewable project, while the remaining value depends on finishing the asset and connecting it reliably to the system.

Source

El Universo

View original
Ecuadorenergywind powerLojaproject finance
Companies: BID Invest, Proparco, FMO
Regions: Loja, Catamayo
Share
Research Support

Support the EcuadorBrief archive.

Research support helps fund review, corrections, and hosting. New publishing is paused.

Newsletter paused

EcuadorBrief is not sending daily briefings while the archive is under review.

Join Chip's personal newsletter

Related Coverage

Energy

Ecuador Bolsters Thermoelectric Capacity Amid Dry Season and El Niño Concerns

Ecuador's National Electricity Operator Cenace reports an average thermoelectric generation of 875 MW between September 1 and September 23, 2026, contributing approximately 19% of national demand. This increase is partly due to two new generation barges, which began operation on September 21, 2026, adding 200 MW.

primicias.ec; primicias.ec; primicias.ec|
Energy

Ecuador's Oil Production Recovers, Government Seeks Private Investment for Sacha Field

Ecuador's average oil production reached 460,562 barrels per day from January to August 2026, marking an 8.1% recovery from the previous year's pipeline disruptions. The government is actively pursuing private investment for the Sacha oil field, with interest from UAE companies, following a previous unfinalized process in 2025.

primicias.ec; primicias.ec|
Energy

Ecuador's Oil Production Targets Face Lower Projections from Central Bank Amidst Shifting Price Outlook

Ecuador's Ministry of Energy aims for 500,000 barrels per day by December 2026, but the Central Bank of Ecuador projects a lower average of 463,013 bpd for 2027. Oil revenues increased significantly in 2026, while future price forecasts anticipate a market correction despite current high prices.

primicias.ec|
Finance

Ecuador's Country Risk Remains Below 500 Points Following J.P. Morgan's New EMBI Methodology Implementation

Ecuador has maintained a country risk score below 500 basic points since January 2026, attributed to a new calculation methodology for the EMBI by J.P. Morgan. This change, implemented in early September, has been applied to historical data, reflecting improved investor and lender optimism and enabling better financing conditions for the nation.

eluniverso.com|
Policy & Regulation

Ecuador and U.S. Forces Conduct Joint Operation, Dismantling Alleged CJNG-Linked Drug Trafficking Network

On the morning of September 24, troops from the U.S. Southern Command, DEA agents, and members of the National Police carried out their first joint operation in Ecuadorian territory. The operation focused on the provinces of Guayas, Los Ríos, and El Oro, leading to the dismantling of a drug trafficking organization with alleged ties to the Jalisco New Generation Cartel (CJNG).

eluniverso.com; eluniverso.com; eluniverso.com|
Opens WhatsApp with a pre-filled message