Elecaustro Cancels 100 MW Emre Bey Barge Procurement After Sercop Objections
Energy

Elecaustro Cancels 100 MW Emre Bey Barge Procurement After Sercop Objections

Chip MorenoChip Moreno||Source: Primicias

Elecaustro declared deserted the procurement process for the Emre Bey floating generation barge after Sercop identified regulatory noncompliance and recommended cancellation.

The contract would have added 100 MW of thermoelectric capacity to reinforce Ecuador’s power supply.

Contract Context

During the 2024 power crisis, when Ecuador imposed blackouts of up to 14 hours per day, the government contracted three floating-generation barges from Turkish company Karpowership at a total cost of USD 250 million.

The contracts for the three vessels ended in 2026. Two of them, Murat Bey and Erin Sultan, will continue operating for at least two more years under new contracts tied to the upcoming dry season.

Emre Bey may not continue unless a new contract is completed. As of the article’s close, Elecaustro had not started a new Sercop procurement process.

Emre Bey Timeline

Emre Bey arrived in Ecuador in August 2024 under a USD 114 million, 18-month contract that ended in March 2026. It continued operating under an extension through the end of May 2026 and had been expected to continue until 2028.

The decision to declare the procurement deserted appears in Resolution No. 2026-0102, signed on June 29, 2026, by Elecaustro general manager Marco Toledo.

The re-contracting budget was USD 155 million for 24 months of generation. Elecaustro opened the process on March 13, 2026, and received one offer on March 26 from Karpowership.

Sercop maintained its observations and, on June 1, 2026, issued a mandatory recommendation that Elecaustro apply Article 31 of the public procurement law and declare the process deserted.

What To Watch

Ecuador sought the 100 MW addition to support a national demand averaging 4.300 MW. Investors and energy users should watch whether Elecaustro reopens procurement, whether Emre Bey exits the system, and whether replacement diesel or floating generation can be contracted before late-year hydrology risk tightens.

Source

Primicias — "Fracasa el intento de contratación de una barcaza, para enfrentar el estiaje de octubre"

View original
ElecaustroSercopKarpowershipEmre Bey
Companies: Elecaustro, Karpowership
Regions: Guayas, Ecuador
Share
Research Support

Support daily Ecuador business intelligence.

Research support funds source monitoring, data checks, editing, publishing, and sector coverage for professionals tracking Ecuador.

Daily Briefing

Ecuador business intelligence, delivered at 6 AM ECT.

Related Coverage

Energy

Ecuador Updates Permit for $277.7 Million Peru Power Interconnector

Ecuador’s environmental-license update advances the Peru interconnection project. The next test is construction and commissioning against the stated 2029 target.

Primicias; Vistazo|
Energy

ITT Equipment Failure Cut Output to About 15,000 Barrels a Day

An ITT processing-system failure interrupted production beginning September 6. The latest cited operating data precede today, so full restoration remains unverified.

Primicias|
Energy

Paute Inflows Enter the Dry Season Below Historical Benchmarks

Ecuador entered the September 2026-March 2027 dry season with below-historical inflows across the Paute system. Mazar averaged 56 m³/s in August versus a historical 90 m³/s, while Paute basin flow averaged 94.8 m³/s against a historical 136.4 m³/s.

Primicias|
Energy

Ecuador Seeks 90-110 MW Barge Extension As Dry-Season Risk Builds

Elecaustro opened a USD 42.7 million process to keep the 90-110 MW Erin Sultan barge operating at Las Esclusas. Cenace warns of a 25% probability of power deficits in the 2026-2027 dry season and says Ecuador needs at least 893.7 MW of additional capacity.

Primicias|
Energy

Energy Supply Brief: 270 MW Offline at Minas San Francisco, Karpowership Barge Renewal Stalled, New Minister's Corporate Ties Under Scrutiny

Ecuador's electricity supply margin tightened further this week as the 270 MW Minas San Francisco plant went offline for mandatory reservoir maintenance through May 16, while the Karpowership Emre Bey barge's contract renewal remains suspended by Sercop procurement objections. Meanwhile, new Energy Minister Juan Carlos Blum's shareholdings in a state-contracting consultancy raise governance questions.

Primicias|
Opens WhatsApp with a pre-filled message