Energy

Cenace Flags Five Transmission Risks Before Ecuador’s 2026 Dry Season

Chip MorenoChip Moreno||Source: Primicias

Ecuador’s electricity risk profile is extending beyond generation capacity. The National Electricity Operator (Cenace) has identified five relevant operational risks in the National Interconnected System (SNI), with most associated with the transmission network.

The assessment matters for industrial users, commercial facilities, logistics operators, and investors because additional megawatts do not eliminate a bottleneck if the grid cannot move that power to the load center. Cenace’s June 2026 operating plan says the SNI is operating under degraded conditions in several points of the country.

The dry-season clock

The warnings arrive ahead of the 2026 dry season, expected from October 2026 through March 2027. Ecuador’s hydroelectric output typically becomes more exposed during that period, raising the value of thermal generation, local reserve, and transmission reliability.

Energy expert José Alvear Campodónico described the issue as a structural weakness in transmission. His point is operationally important: adding generation without expanding the infrastructure that transports it leaves the system exposed to the same constraint.

Five operating risks

The first risk concerns the 230-kV Santa Rosa–Alluriquín–Santo Domingo–Quevedo transmission line. The commercial operation of the Alluriquín plant in the Toachi Pilatón hydroelectric complex increased power transfers through that corridor, but Cenace says there are no expansion projects currently mitigating the overload.

The system is therefore relying on the Systemic Protection System, or SPS, for contingency mitigation. Cenace says using SPS as the principal mitigation tool is neither sustainable nor technically advisable. The system was designed as a last line of defense for severe events, not as a substitute for network expansion.

The second risk is the coincident exit of plants in the Esclusas–Trinitaria–Salitral area. Cenace cites the emergency outage of the 85-MW Trinitaria plant in March 2025, which coincided with maintenance at another Guayas facility. It also cites the emergency outage of Enrique García from October 4 to December 13, 2025, while Trinitaria maintenance was still under way.

The third risk concerns the Milagro–Minas San Francisco–Machala area, where coincident maintenance and unit unavailability have left El Oro vulnerable because of limited local generation and the low power factor of CNEL load.

The fourth involves the linked maintenance of Agoyán and San Francisco. Cenace says there may not be enough resources to guarantee continuity during a contingency in the country’s northeastern zone.

The fifth concerns the floating plants Emre Bey and Murat Bey near the high-demand Trinitaria–Pascuales–Salitral area close to Guayaquil. Murat Bey renewed its contract; Emre Bey was still not operating while its renewal was in process. Cenace warns that losing local reserve could force programmed or automatic load disconnections if another line, plant, or demand event fails at the same time.

What to watch

Track the status of transmission expansions, plant maintenance, Emre Bey’s renewal, local reserve around Guayaquil, and operating conditions as October approaches. The key distinction for business planning is between installed generation and deliverable, reliable power at the location where it is needed.

Source: Primicias

Source

Primicias — "Cenace advierte de cinco riesgos operativos en el sistema eléctrico de Ecuador, a las puertas del estiaje de 2026"

View original
Cenaceelectricitytransmissiondry seasongrid risk
Companies: Cenace, CNEL, Celec EP
Regions: Ecuador, Guayas, El Oro
Share
Research Support

Support daily Ecuador business intelligence.

Research support funds source monitoring, data checks, editing, publishing, and sector coverage for professionals tracking Ecuador.

Daily Briefing

Ecuador business intelligence, delivered at 6 AM ECT.

Related Coverage

Energy

Ecuador Updates Permit for $277.7 Million Peru Power Interconnector

Ecuador’s environmental-license update advances the Peru interconnection project. The next test is construction and commissioning against the stated 2029 target.

Primicias; Vistazo|
Energy

ITT Equipment Failure Cut Output to About 15,000 Barrels a Day

An ITT processing-system failure interrupted production beginning September 6. The latest cited operating data precede today, so full restoration remains unverified.

Primicias|
Energy

Paute Inflows Enter the Dry Season Below Historical Benchmarks

Ecuador entered the September 2026-March 2027 dry season with below-historical inflows across the Paute system. Mazar averaged 56 m³/s in August versus a historical 90 m³/s, while Paute basin flow averaged 94.8 m³/s against a historical 136.4 m³/s.

Primicias|
Energy

Ecuador Enters a September Dry Season With a 450 MW November Deficit Risk

The Vice Ministry of Electricity expects the hydroelectric dry season to begin in September and last into March 2027. Cenace projects a possible 450 MW November deficit, while government procurement delays have reduced the generation expected by December.

Primicias|
Energy

Ecuador Electricity Demand Hits 5,634.31 MW July Record

Ecuador’s electricity demand reached 5,634.31 MW at 19:00 on July 15, the highest level recorded so far in 2026. The peak exceeded the Electricity Master Plan’s 2026 normal-growth projection of 5,206 MW, adding pressure before the October-March dry season.

Primicias|
Opens WhatsApp with a pre-filled message